based on the Critical Path Method (CPM), the network diagram of the work of different audit areas comes as Figure 1, and we can find that the critical path which is the series of activities using the longest time to complete is Activity 1-2-5-7-10-13-15. It means that if there is any delay on Activity 1, 2, 5, 7, 10, 13, 15, the whole project would be delayed also. However, David is only responsible on the auditing of liquid assets which is Activity 4 which is not in the critical path. The vacation…