“Construction planning and scheduling is a logical analysis of a construction project together with all of its parts, and a thorough knowledge of construction methods, materials, and practices” (Mohamed, 2006 cites Fisk, 1997).
To overcome the challenges of expected duration, associated with the PERT method, Monte Carlo simulations can be used as an alternative.
Monte Carlo simulation approach is the system used to consider variability of project component durations and the uncertainty of proliferation factor during the project lifetime and calculates for the cost spread and allocation (Mohamed, 2006). Monte Carlo seems to generally used in risk management as well as CPM and PERT.
In typical Critical Path Method (CPM) scheduling, it is acceptable to have a single point estimate of the amount of time required to perform a particular task. PERT (Program Evaluation and Review Technique) allows analysing the possible evolution of the achievement time taking into account all projects activities and not only those belonging to the critical path. In Monte Carlo Simulation (MCS), each activity in the project has its own range and pattern of duration possibilities.
From PERT analysis applied for estimate of expected duration of the project as shown in previous section it can be discussed that PERT method can be used to help predict the probability & range of values that will measures the actual duration of the project with using normal distribution and beta to determine the probability of each particular task and expected lifetime of project duration.
Monte Carlo simulation is an analysis tool that enables project manager attaches many factors that may cause or contribute to uncertainties and risk, which this simulation data can be calculated many time (Mohamed, 2006).
A simple triangular distribution was used to generate stochastic inputs applied in the Monte Carlo simulation. This requires only three values: a lower limit or “mini- mum,” a mode or “most probable,” and an upper limit or “maxi- mum” value for the criteria.
Figure1: Triangular distribution for W1 (weight percentage)
Figure2: table shows example from Monte Carlo Simulation Approach to Support Alliance Team Selection (EI Asmar et al, 2009) each factor generated with triangular distribution
Monte Carlo
correctly. The restraint strap has not been installed to the correct building regulations. There appears to be bad workmanship and supervision at this work site. It would not have been signed off at this stage of works if it was detected by competent management this would have been achieved by adopting the provisions of schedule 7 of the building regulations 1976. • • • Tension straps should have a declared tensile load capacity of no less than 8 kN and a displacement of not more than 2mm. Strap has not…
project, different types of resources will be utilized. For example, if the project is to design and construct an office building, the project effort might first involve a few architects and engineers in developing the building plans. Then, as construction gets under way, the resources needed will substantially increase to include steelworkers, carpenters, electricians, painters, and the like. The level of effort will decrease after the building is finished, and a smaller number of different…
Emirates Journal for Engineering Research, 10 (2), 23-36 (2005) (Regular Paper) VALUE AND RISK MANAGEMENT PROTOCOL FOR DYNAMIC BRIEF DEVELOPMENT IN CONSTRUCTION A.A.E. OTHMAN Department of Social Services and Commercial Buildings, Abu Dhabi, United Arab Emirates aothman@emirates.net.ae (Received August 2005 and accepted November 2005) اﻟﻨﻈﺮﻳﺎت اﻟﺤﺎﻟﻴﺔ ﻟﻌﻤﻠﻴﺔ اﺳﺘﺨﻼص ﻣﺘﻄﻠﺒﺎت اﻟﻤﺸﺮوع ﺗﺤﺪد ﺗﻄﻮﻳﺮ هﺬﻩ اﻟﻤﺘﻄﻠﺒﺎت اﻟﻲ ﻣﺮﺣﻠﺔ ﻣﻌﻴﻨﺔ. هﺬا اﻟﻤﻨﻈﻮر .ﻳﻌﻮق اﻟﺘﻔﺎﻋﻞ ﺑﻴﻦ اﻟﻤﺎﻟﻚ و اﻟﻤﺼﻤﻢ، آﻤﺎ ﻳﻤﻨﻊ اﻻﺳﺘﻔﺎدة…
a Project? “A project is usually a one-time activity with a well-defined set of desired end results…complex enough that the subtasks require careful coordination and control in terms of timing, precedence, cost and performance.” Project Management: A Managerial Approach, Jack R. Meredith and Samuel J. Mantel, Jr. 1995 The assignment of resources to accomplish specific results (deliverables) with a well-defined schedule and budget. Accenture (1999) “something that is contemplated…
Construction Safety «¿r-Reviewed mm»,,. Quality Ma mi n T An Expanding Role for SH&E Professionals truction gement By Sathy Rajendran, Brian Clarke and Richard Andrews he role of construction safety professionals has significantly expanded over the past decade. The industry employs thousands of safety professionals, most of whom work for contractors (general or subcontractors). Prior to the 1980s, only a few progressive owners held employees and construction contractors…
Assignment front sheet Qualification Unit number and title Extended Diploma in Construction & the Built Environment Unit 7 Project Management in Construction and the Built Environment Learner name Assessor name B HUCKLE Date issued Hand in deadline Submitted on 8th October 2014 5th November 2014 Assignment title The Construction Team and Resource Management In this assessment you will have opportunities to provide evidence against…
D. Brooks – Management – Lesson 3 Management Procurement A method where overall design is the responsibility of the client’s consultants, and the contractor is responsible both for defining packages of work and then for managing the carrying out of this work through separate trades or works contracts. ● Appointment of the contractor is usually by negotiation or tender, and interview. He is paid a management fee. The work packages are let by competitive tender. ● The client will start by appointing…
performance of construction industry. The ILO has made an estimation which there is at least 60,000 fatal accidents a year on construction site around the world. That is one in every six work-related fatal accidents occur on a construction site. Besides that, there is more than 40% of work-related deaths occur on construction sites despite the sector only employing between 6% and 10% of total employment in industrial countries (International Labour Organization, 2012). Construction industry contributes…
Fundamental principle of supply chain management to the success and failure of UK construction industry 1. Introduction Over the past few years, the UK construction industry has been situated in a difficult period due to the effect of recent recession nationally and globally. “Output in the industry fell at a faster rate than total GDP. (Construction industry, Lucinda Maer, 2011)” Despite the return of growth in economy, the progress has been seemingly sluggish at time. Nevertheless, the future…