Publishing as Prentice Hall 8-1 Project Crashing Basic Concept In last lecture, we studied on how to use CPM and PERT to identify critical path for a project problem Now, the question is: Question: Can we cut short its project completion time? If so, how! Chapter 8 - Project Management 2 8-2 Project Crashing Solution! Yes, the project duration can be reduced by assigning more resources to project activities. But, doing this would somehow increase our project cost! How do we strike a balance…