A cost estimating technique based on estimating individual work items and summing them to get a project total.
Select one:
a. Analogous Estimates
b. Bottom-Up Estimates
c. Definitive Estimate
d. Parametric Estimate
Question 2
Correct
Mark 1.00 out of 1.00
Flag question
Question text
A document that describes how cost variances will be managed on the project
Select one:
a. Analogous Estimate
b. Cost Management Plan
c. Earned Value Management
d. Estimate at Completion
Question 3
Correct
Mark 1.00 out of 1.00
Flag question
Question text
A time-phased budget that project managers use to measure and monitor cost performance.
Select one:
a. Cost Baseline
b. Cost Budgeting
c. Cost Estimating
d. Cost Variance
Question 4
Correct
Mark 1.00 out of 1.00
Flag question
Question text
An estimate of the value of the physical work actually completed
Select one:
a. Earned Value
b. Earned Value Management
c. Direct Costs
d. Actual Cost
Question 5
Correct
Mark 1.00 out of 1.00
Flag question
Question text
Considers the total cost of ownership, or develpment plus support costs, for a project.
Select one:
a. Learning Curve Theory
b. Life Cycle Costing
c. Parametric Modeling
d. Rate of Performance
Question 6
Correct
Mark 1.00 out of 1.00
Flag question
Question text
Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.
Select one:
a. Intangible Costs
b. Sunk Cost
c. Tangible Costs
d. Indirect Costs
Question 7
Correct
Mark 1.00 out of 1.00
Flag question
Question text
Dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict.
Select one:
a. Management Reserves
b. Reserves
c. Project Cost Management
d. Cash Flow Analysis
Question 8
Correct
Mark 1.00 out of 1.00
Flag question
Question text
Money that has been spent in the past
Select one:
a. Actual Cost
b. Direct Cost
c. Sunk Cost
d. Indirect Cost
Question 9
Correct
Mark 1.00 out of 1.00
Flag question
Question text
The processes required to ensure that the project is completed within the approved budget.
Select one:
a. Management Reserves
b. Project Cost Management
c. Rate of Performance
d. Planned Value
Question 10
Correct
Mark 1.00 out of 1.00
Flag question
Question text
The ratio between revenues and profits
Select one:
a. Profit Margin
b. Planned Value
c. Profits
d. Actual Costs
Quiz 8th week
In the context of Project Quality Management, a scatter diagram is a
Select one:
a. Quality Control tool or technique
b. Quality Control output
c. Quality Assurance tool or technique
d. Quality Assurance output
e. Quality Planning tool or technique
Question 2
Complete
Mark 1.00 out of 1.00
Flag question
Question text
Quality Assurance is
Select one:
a. Evaluating overall project performance to ensure the project will satisfy the relevant quality standards.
b. Identifying which quality standards are relevant to the project and how to satisfy them.
c. Monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.
d. The graphic display of data that illustrates results of a process over time.
Question 3
Complete
Mark 1.00 out of 1.00
Flag question
Question text
Quality Control is
Select one:
a. Evaluating overall project performance to ensure the project will satisfy the relevant quality standards.
b. Identifying which quality standards are relevant to the project and how to satisfy them.
c. Monitoring specific project results to ensure that they comply with the relevant quality standards while identifying ways to improve overall quality.
d. The graphic display of data that illustrates results of a process over time.
Question 4
Complete
Mark 1.00 out of 1.00
Flag question
Question text
The cost
Related Documents: Essay on Costs and Cost Question
Case #3 Discussion Questions 1. After carefully analyzing the advantages of basing a suppliers overall evaluation on its lowest performance on one of the five dimensions (Quality, Delivery, Cost Management, Technical Support and Wavelength), I have come up with the conclusion that it points out a direct weakness that the supplier has, which most likely is filterable. It also lets you see other options that could be employed for different performance directions if needed. This as well assists…
STRATEGIC COST MANGEMENT COST ESTIMATION Continental Airlines Objective: To advise management about whether cutting flight capacity by 11% will turn Continental into a profitable firm in the near future (within the next year). The report should include information gathered from answering the following questions. Requirement: Read the Continental Case and answer the following questions. The case and data are on Blackboard. 1. Use the quarterly data for operating costs and the various cost drivers…
Multiple Choice Question 49 Which of the following is an advantage of corporations relative to partnerships and sole proprietorships? Harder to transfer ownership. Lower taxes. Most common form of organization. Reduced legal liability for investors. Multiple Choice Question 64 The group of users of accounting information charged with achieving the goals of the business is its creditors. investors. managers. auditors. Multiple Choice Question 110 Which of the following financial…
Question 1 Not yet answered Marked out of 1.00 Flag question Question text Overhead is applied to jobs at a rate of 150% of direct labor costs. Job # 100 required $500 in direct labor costs. The job was initially budgeted to require $550 in direct labor costs. Overhead applied to # 100 during the period amounted to: Select one: a. $550 b. $750 c. $825 d. some other amount. Question 2 Not yet answered Marked out of 1.00 Flag question Question text Which of the following is an example of a direct material…
Question 2 C: For the US the opportunity cost of producing cars is 5 tons of grain each year. The opportunity cost for gain is 2 cars per year. The opportunity cost of cars for Japan is roughly 2.5 tons of grain and the opportunity cost for grain is 2 cars per year. Question 2 D&E: Neither country has an absolute advantage in producing cars, although the opportunity cost is lower for Japan to produce cars because of production limitations on grain. Neither Country has a comparative advantage on…
computed results of your exam. Grades for essay questions, and comments from your instructor, are in the "Details" section below. Date Taken: 11/19/2013 Time Spent: 05 min, 55 secs Question Type: Multiple Choice # Of Questions: 8 Question 1: The following are proper descriptions about the cost functions, EXCEPT: Student Answer: a. In economic terms, cost values include explicit monetary cost plus the value of opportunity cost for o other…
| Question : | (TCO 2) Bubba’s Crawfish Processing Company uses a traditional overhead allocation based on direct labor hours. For the current year overhead is estimated at $2,250,000 and direct labor hours are budgeted at 415,000 hours. Actual overhead was $2,200,000 and actual direct labor hours worked were 422,000. (a) Calculate the predetermined overhead rate. (b) Calculate the overhead applied. (c) Determine the amount of overhead that is over/underapplied. | | | Student Answer:…
LOW NAIL COMPANY Question 1: Using the EOQ methods outlined in chapter 9, how many kegs of nails should Low order at one time? The EOQ formula is: EOQ = √ 2 (annual use in units) (cost of placing an order) / annual carrying cost per item per year = √ 2 (2000) (60) / 2 = √ 120,000 = 345 kegs per order Note the 2 in the denominator. That is because, on average, the rented warehouse space is only half full, which, makes the average warehousing cost per keg be $2. Question 2: Assume all conditions…
Semester 1 2012 TUTORIAL QUESTIONS – TUTORIAL FOUR in WEEK FIVE ASSESSMENT: Worth 1.5%. You must hand in your completed answer sheet (pages 6-7) to the tutor at the beginning of the relevant tutorial. You must attend for the full period of the tutorial to which you have been assigned. PURPOSE of this Tutorial To enable you to: a. to increase your knowledge of production concepts, especially the short-run relationship between outputs and variable inputs and b. the cost side of the firm Note: You…